For travellers using the Gelephu-Trongsa highway, the Boxcut and Ossey stretches remain major concerns, particularly during the monsoon. But there is some relief as the bypass at Ossey nears completion.
Work on a nearly two-kilometre bypass at Ossey is in its final stage. Its blacktopping, which is expected to begin next month, is planned for completion early next year.
Lachuman Mongar, Project Engineer at Sonam Rinchen Construction Private Limited, Gelephu, said, “We expect to complete the works on time, as we have completed most of the tough and complicated parts. Now, we plan to put in more labourers and complete the works soon. The blacktopping works will start from December, and we expect to complete them by January next year.”
For those travelling between Gelephu, Zhemgang and Trongsa, passing through Ossey and Boxcut has been difficult, especially during heavy rainfall. Erosion and road damage disrupt traffic, delay journeys, and often leave commuters and transport operators uncertain about getting through.
Leki Wangchuk, a traveller, said, “The highway road is not in a good condition. It is muddy and causes a lot of inconveniences. I almost lost the vehicle’s control while driving through Boxcut.”
Kalu Ram Subba, another traveller, said, “The road is okay during the dry season, but when it rains, it becomes very difficult to cross. Moreover, during the late hours, the road causes numerous problems for travellers. I have personally seen a truck getting stuck here due to the bad road conditions.”
But the Ossey bypass does not remove the risks altogether. The existing Boxcut stretch will continue to be a challenge along the highway until the alternate route is ready.
The 19.3-kilometre Boxcut bypass is expected to be complete in 2028. It starts from the Gelephu hot spring area, taking a new alignment towards Jigmechoeling Gewog. The project includes five bridges.
As per earlier BBS reports, the government spends about two million ngultrum every three months during the monsoon to clear the Boxcut stretch. The problem has been recurring since 2010.
For now, the Ossey bypass could bring some immediate relief. But the real test will be whether these road improvements, once complete, can make travel more reliable every time the rains return.
Passang Dorji and Karma Wangdi, Gelephu
Edited by Sonam Wangdi